Understanding and Identifying the Critical Path in EPC Projects
- Jinoy Viswan
- Nov 30, 2025
- 6 min read

The Line of Logic That Decides Everything
Every EPC project moves forward on two timelines.
The first is visible.
It is made of drawings, deliveries, workfronts, manpower, inspections, and weekly progress reports. Teams track it carefully. It feels tangible and familiar.
The second timeline is invisible.
It is made of logic, sequence, and dependencies. It exists beneath the surface of the project, shaping progress whether anyone notices or not. This invisible timeline is the critical path.
It governs the earliest completion date. It identifies where delay matters and where it does not. It shows where the project is most vulnerable and where decisions have the greatest impact.
Yet on many EPC projects, the critical path is spoken of more than it is understood. Reports highlight it.Meetings mention it. Everyone refers to it. But when asked to explain what truly drives completion, project teams often give different answers.
This should not surprise us. Critical paths are easy to describe and difficult to demonstrate. Schedulers stare at tangled logic. Planners scroll through thousands of activities. Managers rely on simplified reports. And somewhere inside that complexity lies the true sequence that controls the project’s finish date.
Schedules fail not because the logic is incorrect, but because the assumptions beneath the logic are never examined- Keith Pickavance
His point is simple and practical. A project cannot manage what it cannot see.
The purpose of this article is to make the critical path visible. Not by using complex scheduling techniques, but by explaining the principles that allow EPC teams to identify the true driver of completion. When the critical path can be explained, it becomes a tool of foresight. When it cannot be explained, it becomes a risk.
A clear critical path is not a technical luxury. It is the line of logic that allows a project to understand itself.
1. Why Critical Path Identification Fails in EPC Projects
1.1 EPC schedules contain overwhelming complexity
Engineering, procurement, construction, and commissioning each operate on their own timelines. Each contains hundreds or thousands of activities. When combined into a single schedule, this complexity makes the critical path difficult to see.
This is not a planning failure. It is the natural structure of EPC work.
1.2 The software’s “critical” filter is not the true critical path
Primavera and other CPM tools highlight activities based on internal settings. These settings depend on:
calendars
progress calculation modes
constraints
incomplete logic
float thresholds
relationship types
The software shows what it is told to show. It does not understand constructability. It does not understand the real sequence of work.
The critical path in the tool may not be the critical path in the field.
1.3 Schedule quality issues create false criticality
Schedules often contain quality deficiencies that distort float and logic:
open-ended activities
missing predecessors or successors
excessive constraints
incorrect calendars
activities outside working periods
unmodelled scope
wrong progress settings
The SCL Protocol identifies these issues as primary causes of misleading critical path behaviour. AACE RP 29R 03 lists them as conditions that invalidate forensic analysis.
A schedule with these defects cannot reveal the true critical path.
1.4 EPC projects typically have multiple critical and near critical paths
Process units, utilities, offsites, pipe racks, buildings, and commissioning sequences may each have a path that finishes close to the contractual milestone.
It is normal for an EPC project to have several important drivers. Understanding how they behave is essential to identifying the true controlling sequence.
1.5 Criticality shifts as the project advances
Progress changes logic. Design changes alter sequences. Delivery variations affect relationships. Delays in one area create pressure in another.
Without continuous validation, the critical path seen at the start of engineering may not be the same during construction or commissioning.
This is how projects lose sight of what truly drives completion.
2. What Happens When the Critical Path Is Misidentified
2.1 Strategic decisions lose accuracy
Without a clear critical path, teams focus on visible workloads rather than logical drivers. Acceleration may be attempted in non critical areas. Mitigation may be applied without effect. Management attention becomes reactive.
The project moves, but just not in the right direction...
2.2 Progress reporting becomes misleading
When the critical path is unclear:
early warnings lose meaning
forecasts become unreliable
reports show progress but not causation
meetings focus on activity rather than sequence
Progress becomes movement without insight.
2.3 Delay analysis becomes vulnerable
Delay claims rely on one evidential foundation:
Did the event delay the critical path?
If the critical path is wrong, the delay analysis cannot be defended.
Nicholas Gould has emphasised on multiple occassions, that causation can only be proven if the logic of the critical path is transparent and traceable. A misidentified path destroys entitlement by breaking the causal chain.
2.4 Contractor and owner lose alignment
The contractor may present one view of the drivers.The owner may believe another.
This misalignment leads to disagreement, dispute, and late escalation. A shared understanding of the critical path prevents this breakdown.
2.5 Schedule instability increases risk
False criticality or hidden criticality results in:
poor early warning
confused mitigation
misallocated resources
distorted perceptions of progress
inaccurate claims preparation
The schedule loses its value as a management tool.
3. What EPC Teams Need to Establish a Defensible Critical Path
3.1 A CPM model that reflects actual execution
A critical path is credible only when the underlying model reflects reality.It must include:
complete scope
correct activity relationships
consistent calendars
justified constraints
appropriate durations
Roger Gibson has noted that schedules must reflect how work will be built, not how the modeller wishes it to be built. Logic must follow constructability.
3.2 Meaningful float that reflects true sequencing
Float becomes a useful indicator of criticality only when the schedule is clean. This requires:
removal of open ends
correction of calendar conflicts
reduction of unnecessary constraints
validation of logic
When float reflects reality, the critical path becomes visible.
3.3 A clear chain of driving predecessors
A critical path is defensible when it can be explained. The sequence must be traceable:
activity by activity
predecessor by predecessor
back to the data date
AACE RP 29R 03 and the SCL Protocol both emphasise logic tracing as the basis for reliable analysis.
3.4 A schedule basis that records modelling assumptions
The Schedule Basis Memorandum must document:
calendars
shift patterns
work cycles
constraints
logic rules
progress mode
data sources
Delay analysis depends on the integrity and transparency of assumptions. Without this, the critical path cannot be defended- David Barry
3.5 Alignment between contractor and owner
A shared critical path prevents misunderstanding and unnecessary conflict. It creates:
faster decision making
clearer early warnings
better risk management
more credible forecasts
more straightforward claims resolution
John Uff QC stressed that fairness in administration flows from disciplined record keeping, not retrospective interpretation.
Alignment is that discipline in practice.
4. Evidence Required to Defend the Critical Path
4.1 A transparent logic trace
The critical path must be shown clearly, without reliance on software filters. This is the backbone of defensible delay analysis.
Records and logic must speak for themselves, because narrative cannot replace evidence- Andy Hewitt
4.2 A readable critical path summary
Senior management, owners, and engineers must be able to understand the path within minutes.
A good summary highlights:
the last finishing activity
the main chain of drivers
intermediate merge points
secondary paths
near critical behaviour
Clarity creates confidence.
4.3 Correction of CPM modelling issues
Before identifying the path, the model must be corrected. This includes:
logic validation
calendar alignment
removal of open ends
reduction of constraints
verification of scope completeness
A flawed model cannot produce a reliable path.
4.4 Correlation with major project documents
The critical path must align with:
FEED documentation
execution plans
milestone strategies
procurement sequencing
construction methodology
A mathematical path that does not match operational reality cannot be defended in delay analysis.
Clear, Simple, Educative
What the Critical Path Really Means
The critical path is the chain of work that controls the finish date. Delay here delays the project.Delay elsewhere may not.
Why EPC Projects Often Have Several Critical Paths
Large industrial projects operate across many parallel areas. Several paths may finish close to each other.All require attention.
Why Near Critical Paths Must Be Tracked
A path with little float can overtake the main path quickly. Monitoring only the main path is insufficient.
Why Software Settings Influence What Appears Critical
Calendars, constraints, progress modes, and logic completeness all influence what the tool highlights. Understanding these influences prevents misinterpretation.
Tailpiece
A project schedule is not simply a chart of activities. It is the written logic of how the work must unfold. The critical path is the line within this logic that reveals where time is most vulnerable.
When EPC teams understand the critical path, they understand the project. They know where to focus, how to prepare, and how to protect entitlement. They prevent confusion, reduce conflict, and strengthen decision making.
A clear critical path is not a guarantee of success. But without it, success becomes uncertain.
When teams understand the critical path, they do not merely build the project.
They understand its logic.




Comments