Extension of Time (EOT) Claims in Construction: Nine Key Points Every Contractor Must Master
- Jinoy Viswan
- Sep 21
- 3 min read

Every contract begins with a promise: a start date, a finish date, and a programme in between. Yet construction projects rarely follow the script.
Weather turns. Designs arrive late. Variations creep in. Progress slows.
The contract date stays fixed. Reality does not.
Extension of Time (EOT) claims exist to bridge that gap. They shield contractors from liquidated damages when delays are beyond their control. But many claims collapse, not because the delay was unreal, but because the claim was poorly framed.
An EOT claim is not a plea for sympathy. It is a structured submission, tested clause by clause, and supported by contemporaneous records.
1. What Is an EOT Claim?
At its simplest, an EOT claim is the contractor’s request for more time when events outside their control delay progress. The claim adjusts the contractual completion date to reflect reality.
Without an EOT, the contractor may be penalised for delays they did not cause.
2. Why Are EOT Claims Important?
EOT claims serve one critical purpose: they suspend or reduce the risk of liquidated damages (LDs). Under most contracts, LDs apply automatically if completion is late. A successful EOT claim extends the completion date and protects the contractor’s position.
In tribunal language: LDs cannot run during a period when the employer is responsible for delay.
Tribunals do not ask whether delay was inconvenient. They ask three questions:
Was the delay notified in time?
Was it proven with records?
Was entitlement clearly linked to the contract clause?
Contractors who answer yes succeed. Those who do not, pay LDs.
3. When to Submit an EOT Claim
Cause: Delay event occurs: late drawing, unforeseen condition, or weather.
Effect: Critical path is disrupted.
Entitlement: Under FIDIC Sub-Clause 20.1, notice must be given within 28 days. NEC contracts often require 14 days.
Substantiation: Copy of the drawing register, site log, or weather data showing the date of disruption.
Tribunals enforce these deadlines strictly (Obrascon v Gibraltar [2014] EWHC 1028).
4. Key Elements of an EOT Claim
An EOT claim must contain:
Description of the delaying event.
Evidence of causation.
Demonstration of critical path impact.
Revised completion date.
Each element aligns with the CEES sequence. Without them, entitlement fails.
5. Supporting Documentation
Contracts protect the contractor who protects themselves with records. Required evidence includes:
Contract agreements (entitlement baseline).
Approved programme (critical path reference).
Site diaries, logs, weather records.
Correspondence (RFIs, instructions, minutes).
Tribunals consistently give greater weight to contemporaneous records than to reconstructed narratives.
6. Benefits of EOT Claims
When properly submitted, EOT claims:
Protect against wrongful LD deductions.
Maintain programmes that reflect reality.
Keep employer–contractor relationships commercially balanced.
Provide defensible positions in adjudication, arbitration, or litigation.
7. Common Challenges in EOT Claims
Proving causation between event and critical path.
Maintaining contemporaneous records.
Meeting notice deadlines.
Failure on any of these points weakens entitlement, even where the delay is genuine.
Example (Bad vs. Good)
❌ “Our project is delayed because of the Employer. We expect more time and compensation.”
Vague, emotional, unsubstantiated.
✅ “On 17 January, the Employer’s revised IFC drawings for structural steel were received 21 days late. This delayed mobilisation of Activity S12 on the critical path by 21 days. Pursuant to Sub-Clause 20.1, the Contractor gives Notice and seeks a corresponding EOT.”
Calm, factual, clause-based, and enforceable.
Tribunal Perspective
EOT claims are not tested on fairness. They are tested on compliance. Tribunals examine whether the contractor gave timely notice, maintained records, and demonstrated causation. Contractors who treat the claim as a forensic submission succeed. Those who treat it as an afterthought fail.
Tailpiece
Delays are certain. Entitlement is not.
Some contractors arrive at tribunal with excuses, vague letters, and missing logs. Others arrive with timely Notices, precise records, and contract-based arguments. One pays liquidated damages. The other secures time.
Because an EOT claim is not just paperwork. It is the contractor’s shield.
Handle it carelessly and it fails.
Handle it with discipline and it holds.




Comments